26
Setting the time and date (if required)
During commissioning, or after pro-
longed time out of use, the time and date
need to be reset.
Extended menu:
1. å
2. "Settings"
3. "Time / Date"
4. Set current time and date.
Venting the boiler
1. Close the shut-off valves on the heat-
ing water side.
2.
Remove cover panel A.
3.
Connect the drain hose on valve B
with a drain.
4.
Open air vent valve B and fill valve
C
in the heating return and vent
using mains pressure (flush) until no
more air noise can be heard.
5.
Close valve B and fill valve C in the
heating return, and open the shut-off
valves on the heating water side.
Venting the heating system
1. Close the gas shut-off valve and
switch ON the control unit.
2. Activate venting program (see next
steps).
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5418 193 GB