Commissioning
Carrying out a user check (in conjunction with the LON system)
Communication with the system devices connected to the fault manager is
tested with a user check.
Preconditions:
H The control unit must be programmed as fault manager (code "79:1").
H The LON user number must be programmed in all control units (see page 98).
H The fault manager user list must be up to date (see page 98).
1. Press L and d simultaneously
for approx. 2s.
User check initiated, all 7 arrows
are displayed.
2. Select the required user
with a or b.
3. Activate check with d.
The arrows in the display flash,
until the check is completed. The
display and all key illuminations
of the selected user flash for
approx.60s.
H The arrows stop flashing if both
devices communicate with each
other.
H The display shown will appear
if no communication is
established. Check the LON
connection and encoding
(see page98).
4. For checking further users,
proceed as described under
items 2 and 3.
5. Press L and d simultaneously
for approx. 1s.
User check completed.